What: Home Improvement Project - Part 2
When: March 27 & 28, 2009
Where: Nancy's house
Friday evening schedule - 6:00pm to 8:30pm
* move all furniture out of bedrooms
* clean all floors
* sand & prep floors
* apply 1st urethane coat
* Measure and cut all floor base
* Patch & texture coat wall repairs
Saturday, March 28, 2009 9am - 1:30pm
* Paint all repaired areas
* sand & clean floors
* apply 2nd coat of urethane
* misc repairs
* apply 3rd coat of urethane
* move furniture back into bedrooms.
Sign up to participate @ Men's Ministries table in foyer or @ Men's Life Group on Wednesday evening 6:30pm Room C-209